The building is done!

Vogel Brothers Building Company will be turning the keys over to us on July 31st. We’ve begun packing, our computers will be down for a bit, and then we’ll be consumed with getting ready to open our new facility on September 2nd.
So, we will no longer update this section — you’ll need to come see it for yourself at our Grand Opening on September 27th from 12 to 4:00 at 149 Waubesa Street!

new cabinets   preschool wall  
May 23 , 2008
Cabinets are being installed in classroom and meeting rooms.
  May 23 , 2008
The corridor outside the administrative offices is being paneled with native hardwoods. Windows of various shapes give a view into the offices.
 
new doors   stage development  

May 23 , 2008
Real doors are in throughout most of the building.

  May 23 , 2008
The Lussier Teen Center’s stage is taking shape.
 
gareth   preschool  
April 17 , 2008
Garreth looks over building plans. On the right we see the curved preschool wall which makes for an interesting walk down a long hallway.
  April 17 , 2008
Becky Steinhoff leads tour of new facility, explaining amenities of youth classrooms. New windows are in place — we are looking to the east here. Exisitng brickwalls were cleaned with natural cleaning products.
 
gym interior   gym exterior  
April 17 , 2008
The new gym is about the size of the O'Keeffe Fieldhouse —recessed skylights add natural light. Spacious enough for three volleyball courts and will include a batting cage and pitching machine.
  April 17 , 2008
The new gym building features a covered entrance, and a wet craft room/ pottery studio adjoins gym. The building's design makes it look original to the site.
 
       
finishing cement floors   gym interior  

March 21 , 2008
Cement floors are being polished to prepare them for staining a warm gold color.

 

March 21 , 2008
The gym building will house an office, art room, kiln, locker rooms and storage. The walls are up and telecommunications services are being installed.

 
wallboard   entry to lussier teen center  

March 21 , 2008
Wallboard and telecommunication systems are being installed.

 

March 21 , 2008
Wallboard is going up. Walls are being primed. This photo shows the entryway area of the Lussier Teen Center. The main room of the teen center is to the left. This open area will have ping pong, foos ball and a family room type seating area.

 
new windows_exterior      

March 21 , 2008
About 275 windows are being installed, making a huge difference inside and out.

     
mezzanine meeting room   looking toward teen center  

February 12, 2008
Here you can see the mezzanine
meeting room above the reception desk area. This photo was taken during the lunch hour but you can see evidence of lots of work being done.

  February 12, 2008
The newly poured cement floor looking toward the wall of the new art room at the teen center end of the building.
 
interior walls go up   cement floor is poured  
February 7, 2008
Interior walls are going up and its becoming easier to envision this historic building — transformed.
  February 7, 2008
The cement floor in the center section of the building is being poured.
 
       
art room  _43   future Evjue Community Room  
January 24, 2008
Inside what will be the art room and part of the gym. The art room will house our silk screen printing, pottery and open space for creative art projects.
  January 24, 2008
The Evjue Community room, which will be perfect for wedding receptions, meetings and other special events.
walkway to gym   mezzanine  
January 24, 2008
The walkway from the gym to the main building takes shape. Soon the overhang will be stained to match the gantry.
  January 24, 2008
This photo was taken from the mezzanine meeting room that overlooks the main entry area of the Center.
 
Gym going up   Construction of gym  
November 28, 2007
The gym walls are going up! It looks a little like our very own Stonehenge, doesn’t it?
  November 28, 2007
The building is crawling with construction workers! We’re almost ready for the clerestory windows to go in. The masonry work is progressing with the inside surfaces getting cleaned and refinished.
 

doorways

  new rafters  
November 6 , 2007
Looking north from the Evjue Community Room down thru what will be a main hallway. Orange dots (lower right of doorway) mark height of new poured concrete floor.
  November 6 , 2007
Many of the rafters needs to be replaced with new boards. Natural light abounds in this space!
 
gym- west   gym-east  

November 6 , 2007
Looking west from just south of the new gym, we are seeing the area that will house the teen center. In the foreground we see the west edge of the new gym floor.

  November 6 , 2007
Standing at the edge of the canopied walkway just south of the gym, we are looking east here.
 
wood ceiling_Margo   Becky and Chris Odt look at windows  
August 27, 2007
Margo Tiedt, Project Assistant for our new building, shows off how bright the wooden roof decking is turning out as it gets sandblasted. 

  September 4 , 2007
Becky Steinhoff, GACC Director shows Chris Odt what a great job the citrus-based, environmentally-friendly solution is doing of cleaning almost 100 years of grime off the brick inside and out. 

 
gutting interior      
  windows out
 
August 2007
All the old interior office walls are taken out. For the first time we see the big space that will be the Evjue Community Commons.

  July 2007
The old windows are taken out; we get a brief taste of how dramatic the natural light will be in our new home. The window openings are soon boarded up to protect the property.

 
teardown  
 
June 2007
The outbuildings on the site are torn down. Soil remediation begins.

  March 2007
The ugly siding comes off, revealing creamy brick that’s in pretty good shape and almost 300 windows that are destined to be replaced.

 